Ellevio AB to add at least 2 new transformers to rural network

Jan 23, 2019
Misc
Posted by Patrick Haddad

Swedish distribution company Ellevio Ab has ordered two new transformers to be added to the regional network in Svansåsen, with the possibility of a further four to be added at a later date.

Both transformers are 40 MVA in size and should be delivered in the second or third quarter of 2020. The transformers will be connected to the 145 kV regional network on the HV side and 20 kV on the LV side.

Potential future additions would be one 40 MVA transformer to be added at Finnebäck , two 25 MVA transformers to go to Horsakullen , and one 63 MVA transformer to go to Stöllet, All would be delivered 12 months after call off.

 

Source: Opic

Photo (for illustrative purposes): 40 MVA transformer, Leinau / ordercrazy / Wikipedia / CC0 1.0