Siemens Energy to help stabilise Sudan grid for Egypt power export

Mar 30, 2021
Companies
Posted by Patrick Haddad

The Egyptian Electricity Transmission Company and the Sudanese Electricity Transmission Company have awarded Siemens Energy with a contract to build grid stabilization stations in Sudan which will stabilize the grid and ensure a reliable flow of power from Egypt to Sudan.

The project will improve supply and enhance reliability of power across Sudan. Today, only around 60 percent of the population in Sudan has access to electricity. 

This contract will be the first grid stabilization of scale to be carried out in Sudan and will utilize Siemens Energy’s Static Synchronous Compensator (STATCOM) technology. STATCOM regulates the transmission variations automatically according to the grid conditions. The solution will strengthen and stabilize the power grid by providing reactive power compensation and dynamic voltage support.

“This project will support growth, jobs and economic transformation,” Said Mahmoud Hanafy, Vice President, Siemens Energy Transmission Solutions in the Middle East. “We are proud to contribute to this strategic project which is critical to accelerate energy transition and foster power trade in both countries. The project is also aligned with Siemens Energy’s commitment to accelerate energy access and security in a sustainable and economically sensible way.” 

One of the two stations will be built in the capital of the state of Northern Sudan, Dongola. The second station will be built in the town of Merowe, about 330 kilometers north of Sudan’s capital Khartoum, where the Merowe High Dam is located. The Merowe High Dam is one of the largest hydropower projects in Africa. 

“This project will help Egypt export reliable power to its neighbor, bringing it closer towards its goal of becoming a regional power hub. We are proud to be part of this endeavor and to help Egypt achieve its goals in the region,” said Emad Ghaly, Siemens Energy Egypt’s Managing Director.

Work will commence by March 2021 and the project is expected to be complete within two years.

In 2019, Siemens Energy has completed the energization of Toshka substation, which plays a strategic role in Egypt-Sudan Electric Interconnection project. Egypt has invested in maximizing the country’s power capacity. Siemens Energy’s mega power plants enabled Egypt to boost its generation capacity by 40 percent in less than three years. Now the country is looking to export the surplus energy and become a regional energy hub. 

Source and photo: Siemens Energy