Ad

Hitachi ABB completes capacitor bank for Minnesota transmission project

May 20, 2021
Misc
Posted by Patrick Haddad

Hitachi ABB Power Grids has announced the successful commissioning of a 500 kV – 1400 MVAr series capacitor bank, one of the largest in the world, for Minnesota Power’s Great Northern Transmission Line project.

By enhancing the transfer capability and reliability of the transmission connection between Manitoba and Minnesota, this project will enable Minnesota Power to strengthen its commitment to shift rapidly toward an emission-free energy system.

This deployment of a major 500 kilovolt (kV) transmission line stretching between Winnipeg, Manitoba and Grand Rapids, Minnesota, further highlights the progress of Minnesota Power’s ‘EnergyForward’ strategy to transition to cleaner energy sources while meeting customer expectations for a reliable, stable, and affordable electricity supply. In late 2020, the company became the first utility in the state of Minnesota to deliver 50% renewable energy to its customers and has a goal of achieving 100% carbon-free energy by 2050.

“We are pleased to play such a critical role in helping Minnesota Power increase the availability of clean power to its customers in the region,” said Alireza Aram, Managing Director, Grid Integration business, North America, Hitachi ABB Power Grids. “This new series capacitor bank, one of the largest in the world, will enable Minnesota Power to meet its customers’ energy needs while increasing system reliability, and support their efforts to reduce carbon emissions from their operations.” 

“This project represents an important contribution to the development of our Great Northern Transmission Line project, part of an innovative delivery and storage system that is enabling us to deliver  50 percent renewable energy to our customers,” said Josh Skelton, Minnesota Power Chief Operating Officer. “Hitachi ABB Power Grids has been a valuable partner in support of our EnergyForward strategy to shift toward carbon-free power.”

“This collaboration with Minnesota Power demonstrates our continuous commitment to help our customers bring renewable electricity to their local communities,” said Anthony Allard, Head of North America, Hitachi ABB Power Grids. “As we transition toward electricity as the backbone of the energy system, the smooth transmission of renewable power between regions and across borders will be increasingly critical.”  

Source and image courtesy of Hitachi ABB

Comments

Leave a reply

Your email address will not be published. Required fields are marked *